FACILITY PROFILE · AZ

Project Blue

Beale Infrastructure · AZ

PROJECT FACTS

Facility overview

Under Construction
Operator
Beale Infrastructure
Location
Pima, AZ
Operating power capacity
Not publicly reported
Planned power capacity
600.0 MW
AI classification
Likely
Source confidence
Confirmed
Reported energy source
grid
Reported utility
Tucson Electric Power (TEP)
Cooling system
closed_loop
Location accuracy
exact
Original announcement
Not publicly reported
Source record updated
2026-09-23

Operating MW and planned MW are separate disclosures, not automatically additive. Blank values mean no established source figure; they do not mean zero. Geolocation may be approximate or represent multiple sites.

SOURCE DOCUMENTATION

Original source links

Pima County NDA confirms Amazon is behind Project Blue data center ↗2026-07-09

HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) ↗2026-07-23

Construction begins on first hyper-scale data center in Pima County ↗2026-08-28

As Project Blue data center construction starts near Tucson, protesters rally outside ↗2026-08-28

Pima County Administrator memo to the Board of Supervisors, 'Update on Project Blue' (17 Sept 2025), with the Beale Infrastructure letter attached — 'we have selected an air cooling technology that uses a closed-loop system... Beale's air cooled design will consume no water, potable or otherwise, for industrial cooling.' ↗2026-08-31

Pima County official Project Blue FAQ, Economic Impact Study section — "180 new full-time, permanent jobs created by the third year of operations in 2029." ↗2026-09-23

Construction Begins on Project Blue, Pima County's First Hyperscale Data Center ↗2026-09-10

RELATED MARKET INTELLIGENCE

Research beyond this dataset

Connect project activity and reported capacity to power, grid and resilience markets.

Explore all studies →
Grid · Market outlook

Data Center Power System Market Size, Share & Industry Analysis, By Type (UPS Systems, HVDC Systems, Solid-State Transformers, AC-DC Converters), By Application (Hyperscale Data Centers, Colocation Facilities, Enterprise Data Centers, Edge Computing Sites, Others), By End User (Cloud Service Providers, Telecommunication Companies, Financial Institutions, Government Entities), By Power Architecture (Centralized Power Distribution, Distributed Power Architecture, Hybrid Power Solutions), and Global Forecast, 2026?2034

Grid connections, transformers and substation market research

Read report overview →

Related studies are selected automatically from the report database. These published market studies address commercial markets. Facility records and grid-demand figures do not independently estimate their revenues.