FACILITY PROFILE · OH

Bitdeer Shalersville Data Center Campus

Bitdeer · Shalersville Township · OH

PROJECT FACTS

Facility overview

Proposed
Operator
Bitdeer
Location
Shalersville Township, Portage, OH
Operating power capacity
Not publicly reported
Planned power capacity
750.0 MW
AI classification
Likely
Source confidence
Reported
Reported energy source
grid
Reported utility
Ohio Edison (FirstEnergy)
Cooling system
closed_loop
Location accuracy
approximate
Original announcement
Not publicly reported
Source record updated
2026-09-21

Operating MW and planned MW are separate disclosures, not automatically additive. Blank values mean no established source figure; they do not mean zero. Geolocation may be approximate or represent multiple sites.

SOURCE DOCUMENTATION

Original source links

Local developer, global tech firm plan major data center project in Portage County ↗2026-09-21

Data center discussion spans 3+ hours as Shalersville mulls 257-acre project ↗2026-07-10

Bitdeer looks to develop 750MW data center campus in Ohio ↗2026-07-10

Asian crypto mining company and Geis partner to bring data center to Shalersville ↗2026-07-10

HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) ↗2026-07-23

RELATED MARKET INTELLIGENCE

Research beyond this dataset

Connect project activity and reported capacity to power, grid and resilience markets.

Explore all studies →
Grid · Market outlook

Data Center Power System Market Size, Share & Industry Analysis, By Type (UPS Systems, HVDC Systems, Solid-State Transformers, AC-DC Converters), By Application (Hyperscale Data Centers, Colocation Facilities, Enterprise Data Centers, Edge Computing Sites, Others), By End User (Cloud Service Providers, Telecommunication Companies, Financial Institutions, Government Entities), By Power Architecture (Centralized Power Distribution, Distributed Power Architecture, Hybrid Power Solutions), and Global Forecast, 2026?2034

Grid connections, transformers and substation market research

Read report overview →

Related studies are selected automatically from the report database. These published market studies address commercial markets. Facility records and grid-demand figures do not independently estimate their revenues.