FACILITY PROFILE · TN

Meta Gallatin Data Center Campus

Meta · Gallatin · TN

PROJECT FACTS

Facility overview

Operational
Operator
Meta
Location
Gallatin, Sumner, TN
Operating power capacity
300.0 MW
Planned power capacity
300.0 MW
AI classification
Confirmed
Source confidence
Confirmed
Reported energy source
mixed
Reported utility
TVA
Cooling system
air
Location accuracy
exact
Original announcement
2022
Source record updated
2026-09-21

Operating MW and planned MW are separate disclosures, not automatically additive. Blank values mean no established source figure; they do not mean zero. Geolocation may be approximate or represent multiple sites.

SOURCE DOCUMENTATION

Original source links

Meta brings data centers in tents to Gallatin, Tennessee ↗2026-07-06

Tennessee has 60 data centers; Nashville probably has more than you think ↗2026-07-06

Meta data center begins operations in Gallatin ↗2026-07-06

Why is Gallatin giving Woolhawk a tax break? ↗2026-07-06

Meta expands Gallatin data center — cooling & water approach ↗2026-07-06

Meta Data Centers blog — Gallatin, we are online! ↗2026-07-25

Gallatin offers a glimpse at hyperscale data center experiences ↗2026-09-09

Meta Gallatin Data Center info sheet (PDF): $1.5B+ investment, 100+ operational jobs, TVA energy planning, water stewardship, 100% clean and renewable energy matching ↗2026-09-21

RELATED MARKET INTELLIGENCE

Research beyond this dataset

Connect project activity and reported capacity to power, grid and resilience markets.

Explore all studies →
Grid · Market outlook

Data Center Power System Market Size, Share & Industry Analysis, By Type (UPS Systems, HVDC Systems, Solid-State Transformers, AC-DC Converters), By Application (Hyperscale Data Centers, Colocation Facilities, Enterprise Data Centers, Edge Computing Sites, Others), By End User (Cloud Service Providers, Telecommunication Companies, Financial Institutions, Government Entities), By Power Architecture (Centralized Power Distribution, Distributed Power Architecture, Hybrid Power Solutions), and Global Forecast, 2026?2034

Grid connections, transformers and substation market research

Read report overview →

Related studies are selected automatically from the report database. These published market studies address commercial markets. Facility records and grid-demand figures do not independently estimate their revenues.