Explore Energy Resources Insights

Explore the Report Store
Let’s talk research +91 94251 50513 [email protected]
FACILITY PROFILE · GA

Microsoft Fairwater Atlanta (Azure AI Superfactory)

Microsoft · Fayetteville · GA

PROJECT FACTS

Facility overview

Operational
Operator
Microsoft
Location
Fayetteville, Fayette, GA
Operating power capacity
Not publicly reported
Planned power capacity
1,500.0 MW
AI classification
Confirmed
Source confidence
Confirmed
Reported energy source
grid
Reported utility
Georgia Power
Cooling system
closed_loop
Location accuracy
exact
Original announcement
2025
Source record updated
2026-07-26

Operating MW and planned MW are separate disclosures, not automatically additive. Blank values mean no established source figure; they do not mean zero. Geolocation may be approximate or represent multiple sites.

SOURCE DOCUMENTATION

Original source links

From Wisconsin to Atlanta, Microsoft connects datacenters to build its first AI superfactory ↗2026-07-07

Microsoft launches Atlanta Fairwater data center, two stories, no UPS or gen sets ↗2026-07-07

Microsoft debuts AI 'superfactory' data center south of Atlanta ↗2026-07-08

Behind Fayette's QTS water controversy: a missed meter, 8,000 workers ↗2026-07-08

Microsoft Fairwater Atlanta: a grid-only gigawatt AI data center ↗2026-07-08

Georgia data center boom: what it's like to have one in your community ↗2026-07-08

Incentives & tax rates ↗2026-07-08

RELATED MARKET INTELLIGENCE

Research beyond this dataset

Connect project activity and reported capacity to power, grid and resilience markets.

Explore all studies →
Grid · Market outlook

Data Center Power System Market Size, Share & Industry Analysis, By Type (UPS Systems, HVDC Systems, Solid-State Transformers, AC-DC Converters), By Application (Hyperscale Data Centers, Colocation Facilities, Enterprise Data Centers, Edge Computing Sites, Others), By End User (Cloud Service Providers, Telecommunication Companies, Financial Institutions, Government Entities), By Power Architecture (Centralized Power Distribution, Distributed Power Architecture, Hybrid Power Solutions), and Global Forecast, 2026?2034

Grid connections, transformers and substation market research

Read report overview →

Related studies are selected automatically from the report database. These published market studies address commercial markets. Facility records and grid-demand figures do not independently estimate their revenues.