FACILITY PROFILE · WA

Vantage WA13

Vantage Data Centers · Quincy · WA

PROJECT FACTS

Facility overview

Operational
Operator
Vantage Data Centers
Location
Quincy, Grant, WA
Operating power capacity
64.0 MW
Planned power capacity
Not publicly reported
AI classification
Not classified
Source confidence
Confirmed
Reported energy source
hydro
Reported utility
Grant County PUD
Cooling system
closed_loop
Location accuracy
approximate
Original announcement
Not publicly reported
Source record updated
2026-09-05

Operating MW and planned MW are separate disclosures, not automatically additive. Blank values mean no established source figure; they do not mean zero. Geolocation may be approximate or represent multiple sites.

SOURCE DOCUMENTATION

Original source links

Vantage Data Centers Completes Development of 89MW, $1 Billion Quincy, Washington Campus ↗2026-09-05

Quincy, Washington Data Center Campus ↗2026-09-05

Quincy, WA data center facility directory (Vantage WA11/WA12/WA13) ↗2026-09-05

RELATED MARKET INTELLIGENCE

Research beyond this dataset

Connect project activity and reported capacity to power, grid and resilience markets.

Explore all studies →
Grid · Market outlook

Data Center Power System Market Size, Share & Industry Analysis, By Type (UPS Systems, HVDC Systems, Solid-State Transformers, AC-DC Converters), By Application (Hyperscale Data Centers, Colocation Facilities, Enterprise Data Centers, Edge Computing Sites, Others), By End User (Cloud Service Providers, Telecommunication Companies, Financial Institutions, Government Entities), By Power Architecture (Centralized Power Distribution, Distributed Power Architecture, Hybrid Power Solutions), and Global Forecast, 2026?2034

Grid connections, transformers and substation market research

Read report overview →

Related studies are selected automatically from the report database. These published market studies address commercial markets. Facility records and grid-demand figures do not independently estimate their revenues.