Offshore Grids and Energy Islands in 2026: Bornholm, Princess Elisabeth and Hybrid Networks

Bornholm and Princess Elisabeth illustrate two offshore-grid financing and execution models. This briefing separates island civil works, hybrid links, regulatory progress and grid asset procurement.

Offshore electricity hubs are evolving from a network-planning concept into multiple project types with real procurement and financing milestones. Bornholm is an international hybrid connection in development; Belgium’s Princess Elisabeth Island has physical marine works and a signed second-phase financing facility.

These projects should not be treated as interchangeable. A man-made island, an offshore converter platform, a radial wind connection and a hybrid interconnector have different cost-sharing structures, electrical architectures and construction risk.

2 GWBornholm–Germany interconnector · planned
€1bnEIB facility signed for Princess Elisabeth Phase 2
2036Bornholm full-project target · official site
01 / THESIS

The offshore grid is becoming a portfolio of different asset classes

A radial connection carries electricity from a wind farm to a national onshore network. A cross-border interconnector allows power trading between systems. An offshore hybrid asset combines at least part of those functions, potentially reducing duplicated subsea routes and creating new dispatch possibilities. An energy island may provide physical space for substations and converter installations; it does not necessarily imply a fully meshed multi-terminal HVDC network. The European Commission’s North Seas Energy Cooperation and ENTSO-E’s Offshore Network Development Plan frame these concepts as coordinated infrastructure needs, not a collection of fully sanctioned projects. [OG51-06] [OG51-07]

Coordination matters because offshore generation, cable landing points, grid capacity, market zones and ownership rarely advance on the same timetable. Governments can agree common ambitions while individual utilities still need permits and defined recovery mechanisms. The 2026 North Sea Summit declarations restated political cooperation and measures to reduce cross-border investment risk, but declarations do not themselves procure offshore hardware. The development pipeline must be read in stages: strategic planning, bilateral agreement, procurement, financed civil work, converter installation and eventual operation. [OG51-10]

The strongest 2026 evidence comes from distinct phases of Bornholm and Princess Elisabeth. One demonstrates cross-border commitments and vendor procurement, the other a tangible offshore construction and financing sequence. Both reveal how the value of energy islands lies in electrical coordination and site infrastructure as much as in the new offshore wind capacity they may connect.

02 / MODELS

Project comparison: what is committed, financed or still conditional

Bornholm Energy Island, Princess Elisabeth Island and North Sea offshore converter platforms serve related but different functions. The projects can be compared by asset scope, published capacity where applicable and latest confirmed stage, but a mixed list of gigawatts, credit facilities and marine work cannot be summed to produce a market-revenue estimate. [OG51-02] [OG51-04] [OG51-09]

ENTSO-E’s ONDP explicitly translates non-binding national offshore renewable objectives into possible transmission corridors and equipment requirements. It is valuable for where electrical investment might be needed, particularly when cross-border operation could avoid redundant landfalls. It does not replace seabed surveys, site-specific cost-benefit analysis or regulatory approval. Similarly, the regulatory discussion around British offshore hybrid assets acknowledges potential efficiencies in combining wind export and interconnection without proving that all such configurations will secure consent or an investable commercial structure. [OG51-07] [OG51-08]

This distinction is fundamental for suppliers. An offshore foundation or caisson contract may be executable years before a future DC topology is fully resolved. Conversely, an HVDC converter contract may be awarded while environmental procedures and long cable construction remain unfinished. The supplier should not infer simultaneous equipment demand from an island branding announcement.

Selected named project and regulatory evidence checked 18 November 2026. Figures use different units and scopes.
Asset / programmeGeographyPublished measureLatest verified statusProcurement interpretation
Bornholm Energy IslandDenmark / Germany2 GW Germany route; ±525 kVAgreement / permits / supplier awards2034 route target; whole programme expected 2036 [OG51-02]
Princess Elisabeth Island, Phase 2Belgium / North Sea€1bn signed EIB facilityMarine island build / financingPhase 2 total cost approx. €2.296bn [OG51-05]
NSC2 offshore converter platformGermany / North Sea2 GW conversion platform2026 contract awardedNot an artificial energy island [OG51-09]
Offshore Hybrid Asset modelGreat BritainNo single capacity totalRegulatory framework / project developmentCombines export and cross-border exchange [OG51-08]
ENTSO-E ONDP corridorsEuropean sea basinsStrategic equipment and corridor needsPlanning, not project approvalFuture connections remain conditional [OG51-07]
03 / BORNHOLM

Bornholm turns a cross-border agreement into a phased engineering programme

Denmark and Germany reached a bilateral investment agreement in January 2026, building on earlier infrastructure supplier decisions. The project aims to connect offshore wind near Bornholm and create a shared electrical route toward Zealand and Germany. 50Hertz describes the German connection as a 2 GW link at ±525 kV with planned commissioning in 2034. Its project page also lists the necessary approval procedures for marine and onshore sections, including the planned German transformer and converter station. [OG51-01] [OG51-02]

The project’s own website says Danish environmental permission has been granted for onshore and offshore facilities and cable works, while the German link follows a separate assessment process. The site also records Siemens Energy’s high-voltage equipment role and NKT’s cable responsibilities. Critically, its full project timeline—including offshore wind generation—is expected to extend to 2036. The 2034 interconnector target and 2036 full-programme expectation describe different scopes rather than an arithmetic contradiction. [OG51-03] [OG51-02]

Technically, Bornholm must manage more than one DC route and multiple AC interfaces as power moves between generation, island and national grids. Converter protection, reactive-power control, local fault behaviour, communication arrangements and system-operator handover need to be coordinated across jurisdictions. Commercially, the challenging work is benefit allocation: which consumers finance capacity that can improve security in more than one national market, and how are changes in wind-farm delivery incorporated into the agreed programme?

Long-lead electrical equipment and cable capacity may be booked well ahead of energisation. That provides a direct supplier opportunity, but the owner must synchronise delivery slots with remaining permits, landing works and civil construction. A strong equipment order book does not eliminate the probability of commissioning slippage if a cross-border approval or market rule changes.

04 / BELGIUM

Princess Elisabeth demonstrates the value of separating civil works from future power flows

Belgium’s Princess Elisabeth Island is a purpose-built offshore hub around 45 km from the coast. Its physical island provides a platform for consolidating offshore power infrastructure and future network connections. In September 2026 the European Investment Bank confirmed a €1 billion green credit facility for Phase 2, while its project register records a signed financing date of 17 July 2026 and an approximate Phase 2 cost of €2.296 billion. The credit facility and project cost describe financing and capital needs, not electricity-market revenue. [OG51-04] [OG51-05]

EIB’s announcement presents the hub as a way to integrate future Belgian offshore wind generation and potentially support a later interconnector with the United Kingdom. A future cross-border route remains a distinct investment and regulatory question, rather than a guaranteed commissioning outcome of island civil construction. Treating every anticipated connection as an awarded cable or converter order would overstate the committed supply-chain pipeline. [OG51-04]

The financing step is important because specialised marine infrastructure carries different risk from installing a substation on land. Offshore access windows, weather exposure, foundation and scour design, cable pull-in arrangements, corrosion protection, safety systems and lifetime maintenance determine both capital cost and the achievable reliability of the hub. Construction of the civil asset creates the physical option for later electrical expansion but does not substitute for signed grid-service arrangements.

05 / ENGINEERING

Hybrid offshore networks demand new protection and operational arrangements

Meshed or hybrid offshore grids add operational flexibility but also multiply interfaces. For radial HVDC export, a dedicated converter and cable pair can usually be studied as a defined connection. Multi-terminal operation raises questions about DC fault isolation, coordinated voltage control, selective protection, converter interoperability and a dispatch hierarchy spanning system operators. ENTSO-E’s planning framework and RDI priorities point to increasing need for coordinated equipment standards, simulation tools and multi-vendor testing as the geography of offshore power grows more complex. [OG51-07]

On a physical island, some equipment can be reached by vessel more easily than on a high-elevation converter platform, but the island introduces its own reclamation, marine civil and environmental burdens. A platform may minimise landform footprint yet have tight topside weight, cooling and maintenance restrictions. A radial connection often has fewer commercial counterparties than a hybrid asset serving two or more markets. These constraints mean there is no universal lowest-cost offshore hub design.

Engineering specifications should separate capacity at the offshore wind connection from the rating of individual export routes. For example, the 2 GW planned Bornholm–Germany link does not alone quantify total future generation or annual transmitted energy. Power-flow studies have to account for simultaneous contingencies, converter availability and contractual dispatch rights. Cost assessment should include redundancy, repair time and access assumptions rather than rely on nameplate MW alone. [OG51-02]

06 / COMMERCIAL

Financing and regulation can be as constraining as marine construction

Cross-border hybrid projects create a classic mismatch between the locations of assets, generators and beneficiaries. If one side pays for capacity that mostly relieves congestion elsewhere, regulated cost recovery becomes controversial. National regulators and transmission owners must reconcile permitted revenue, expected trading rents, offshore-wind connection charges and the risk of future generation arriving late. Ofgem’s discussion of offshore hybrid assets reflects the potential value of integrated solutions, but commercial frameworks must still be adapted to particular projects. [OG51-08]

The EIB’s signed support for Princess Elisabeth demonstrates one financing response: long-tenor infrastructure credit can reduce financing-cost pressure for assets with regulated or strategic functions. Bornholm’s 2026 agreement illustrates another: bilateral government participation can advance a project that crosses ownership and market boundaries. The financing routes differ, and neither guarantees that all future extensions will be built. [OG51-01] [OG51-04]

Supply-chain demand spreads across dredging and marine construction, steel and concrete structures, offshore switchgear, converter electronics, transformers, submarine cable manufacture and installation, digital protection and maintenance vessels. Contractors able to coordinate marine interfaces and power-system testing have an advantage, but the build sequence varies by project. NSC2’s 2 GW offshore platform award in 2026 confirms real industrial capacity being contracted for North Sea export infrastructure; it is a converter platform, not the same civil asset class as Princess Elisabeth Island. [OG51-09]

07 / OUTLOOK

The route to 2034 is selective construction, not a uniform offshore supergrid

Over the remaining years of this decade, project owners will be judged by signed cable and converter packages, environmental permissions, financing arrangements, foundation completion and confirmed market access. Bornholm’s staged approval process and Princess Elisabeth’s Phase 2 financing are practical markers of transition beyond high-level ambition. Yet an island cannot become a highly interconnected trading hub merely because one national export circuit is completed. [OG51-02] [OG51-05]

Longer-horizon plans from ENTSO-E and the North Seas Energy Cooperation may guide manufacturing capacity and seabed-corridor decisions, but suppliers should segment prospective demand by maturity. The most immediately actionable orders sit in civil and electrical packages already contracted. Later multi-terminal additions require additional agreement on control, protection, ownership and cost sharing before their equipment lists can be treated as firm.

By 2034, measurable commercial progress will be the number of offshore interfaces energised with proven operational rules, not simply the number of sea-basin maps showing new hubs. The sector’s long-term opportunity is substantial in engineering breadth, but financing discipline and interoperability will decide how much of that ambition becomes dependable power transmission.

08 / PRIMARY REFERENCES

Primary sources

  1. [OG51-01] German Federal Ministry for Economic Affairs and Energy — Denmark–Germany investment agreement on Bornholm Energy Island (2026-01-26)
  2. [OG51-02] 50Hertz — Bornholm Energy Island Germany–Denmark connection
  3. [OG51-03] Bornholm Energy Island project — Project milestones, supplier agreements and permits
  4. [OG51-04] European Investment Bank — Elia secures €1 billion credit facility for Princess Elisabeth Island (2026-09-07)
  5. [OG51-05] European Investment Bank — Princess Elisabeth Island Phase 2 project details (2026-07-17)
  6. [OG51-06] European Commission — North Seas Energy Cooperation
  7. [OG51-07] ENTSO-E — What are Offshore Network Development Plans? (2026-11-13)
  8. [OG51-08] Ofgem — Interconnection and Offshore Hybrid Assets
  9. [OG51-09] Eiffage — NSC2 North Sea offshore converter award (2026-06-18)
  10. [OG51-10] European Commission — North Sea Summit offshore-energy declarations (2026-01-26)