VSC-HVDC in 2026: Modular Converters, SunZia and the Next Grid-Control Frontier

SunZia demonstrates multi-gigawatt operational VSC-HVDC. The research examines converter architectures, weak-grid operation, procurement economics and multi-terminal development risks.

Voltage-source-converter HVDC has moved beyond compact subsea links into multi-gigawatt power corridors. Hitachi Energy reported the 3,000 MW, ±525 kV SunZia system operational in June 2026, while European transmission owners are awarding further converter work for long onshore and offshore connections.

The next competitive frontier is not only higher ratings. It is how modular converters behave under weak-grid conditions, deliver specified voltage support, coordinate faults and interoperate in increasingly complex hybrid AC/DC networks.

3,000 MWSunZia, U.S. · operating since 2026
±525 kVSunZia bipolar transmission voltage
2 GWNSC2 offshore converter · awarded 2026
01 / THESIS

The strongest VSC market evidence is a commissioned multi-gigawatt link

Hitachi Energy’s June 2026 commissioning notice states that the SunZia project connects renewable generation in New Mexico with the Arizona grid across roughly 550 miles of overhead line. The installed HVDC Light system uses a voltage-source-converter architecture and is designed to transfer up to 3,000 MW at ±525 kV. The supplier describes the link as fully operational; that verified status is different from an announced order or a projected transfer requirement. Rated capacity is not a record of annual electricity transmitted. [VS52-01]

SunZia shows that VSC technology is credible for very large, onshore, long-distance corridors rather than only short subsea connections or urban infeed. Its relevance extends to controllability and AC-system support, especially where generation profiles change quickly. At the same time, it cannot be used to infer a global 2026 VSC installation volume: the system is one named project, albeit at a substantial rating, and its manufacturing contracts may span prior financial years.

Additional evidence comes from Germany and the UK, where major VSC-compatible converter equipment and HVDC construction programmes remain at different procurement stages. The supplier reference for SuedLink DC3 identifies a 2 GW converter and transformer package. National Grid’s March 2026 EGL3 notice confirms Hitachi Energy’s converter-station award, but awards are not equivalent to operating links. Commercial analysis should track units of equipment, completion stage and factory workload rather than add disparate project ratings as if they were this year’s revenue. [VS52-06] [VS52-05]

02 / TECHNOLOGY

MMC converters have changed the technical choice between AC and DC

Line-commutated HVDC relies on thyristor valves and on the connected AC system for commutation. In certain strong-grid bulk-transfer cases it can remain attractive, but it imposes different reactive-power and filtering requirements. Voltage-source converters use self-commutated switching devices and typically a modular multilevel converter, or MMC, topology. Each arm contains many submodules and their capacitors, allowing a synthesised voltage waveform with relatively low harmonic content. Siemens Energy’s HVDC PLUS literature identifies MMC as the established VSC design family, while Hitachi Energy markets its HVDC Light system for both subsea and land transmission. [VS52-02] [VS52-03]

MMC design produces a different procurement bill: power-semiconductor modules, capacitors, arm reactors, fibre-optic gate controls, cooling, bypass and protection functions, and sophisticated converter-transformer and DC insulation interfaces. Redundancy strategies, submodule replacement policy and controls version management matter to long-term availability. The semiconductor and capacitor supply chain is therefore part of the transmission reliability discussion, not simply a cost line inside an electronic cabinet.

High ratings are achievable through coordinated station design, but a vendor’s published top-end capability is not a substitute for project validation. Insulation coordination, harmonic and transient studies, AC voltage limits, cooling redundancy, power loss objectives and DC fault performance must be checked for the exact network. Converter behaviour can be materially different at low system strength or when the system operator asks for unusually rapid support during faults. [VS52-02] [VS52-03]

Selected named project and regulatory evidence checked 18 November 2026. Figures use different units and scopes.
Asset / programmeGeographyPublished measureLatest verified statusProcurement interpretation
SunZia HVDC LightUnited States3,000 MW; ±525 kVOperational June 2026Named VSC installation; ~550-mile route [VS52-01]
SuedLink DC3, Siemens packageGermany2 GW converter and transformer scopeVendor project referenceGrid transfer rating, not annual output [VS52-06]
EGL3 converter stationsUnited Kingdom690 km complete linkConverter supplier awarded March 2026Not yet an operating DC system [VS52-05]
NSC2 offshore converterGermany / North Sea2 GWContract awarded, June 20262034 target, no operation yet [VS52-08]
Bornholm–Germany HVDCDenmark / Germany2 GW; ±525 kVPermitting and designPlanned 2034 interconnector [VS52-09]
03 / PROJECTS

The project ladder runs from operation to construction to awarded equipment

Public sources document a progression of commitment rather than a uniform installed base. SunZia is a commissioned VSC project; SuedLink DC3 is a defined vendor project scope; EGL3 has converter and cable suppliers selected; and NSC2 is an awarded 2 GW offshore converter platform with a commissioning target late in 2034. These status differences determine which technical claims can be stated as demonstrated operation and which remain engineering expectations. [VS52-01] [VS52-05] [VS52-08]

The offshore case adds platform and marine interfaces to the electrical package. Eiffage describes NSC2’s NSORe–Siemens Energy consortium scope as including construction and handover of an offshore platform and related facilities. DC link availability will ultimately depend on valve and transformer performance as well as offshore access, cable repair, marine weather and service logistics. A converter that performs well in factory tests still needs system-level acceptance on the completed transmission route. [VS52-08]

Bornholm’s planned 2 GW, ±525 kV connection shows the other side of the opportunity: projects can have specific engineering parameters while remaining subject to multiple permit procedures. Unlike an operational installation, the commercial and technical outcome remains conditional on construction, verification and commissioning. It is useful as a long-lead equipment signal, not as evidence of annual dispatched power. [VS52-09]

04 / GRID

Grid-forming functions must be specified rather than assumed

One attraction of VSC-HVDC is its ability to command active and reactive power rapidly and support voltage where conventional generation is scarce. Yet vendor descriptions of grid-forming or black-start-related features are not blanket guarantees for every VSC project. Performance depends on software control modes, current limits, storage or energy availability, the network restoration plan and the tests required by the system operator. A system may be technically able to regulate voltage without being contracted or permitted to energise a dead AC island. [VS52-04] [VS52-02]

Weak-grid studies should examine converter synchronisation, interactions with other inverter-based resources, harmonic and sub-synchronous phenomena, protection sensitivity and restoration behaviour. For a major DC export link, disturbances can propagate across several connected AC systems. These models need validation using manufacturer data and test regimes under the conditions most likely to stress the network. Grid-forming, fault ride-through and reactive support are separate requirements, even when implemented in the same converter control software.

The commercial premium for advanced controls is real only when grid owners can measure and value their contribution. Procurement should establish the guaranteed response envelope, measurement location, acceptance test, availability definition, control update process and cyber-security obligations. Without that clarity, an attractive functionality label creates post-award disputes between the converter supplier, protection contractor and network operator.

05 / INTEROPERABILITY

Multi-terminal systems remain an engineering and governance challenge

Point-to-point VSC projects are already operating at gigawatt scale, but meshed and multi-terminal DC networks introduce a different level of system protection. The DC network has no natural AC current zero crossing; rapid fault detection and isolation must be engineered into the protection philosophy and hardware. Converter vendors need compatible control interfaces and agreed behaviours when power flows are reconfigured among multiple terminals. Existing bilateral links do not automatically demonstrate those capabilities.

ENTSO-E’s 2024–2034 RDI roadmap identifies development of critical multi-terminal HVDC components, converter interoperability, simulation and testing facilities, and eventually multi-vendor demonstrations. The roadmap presents these as research and demonstration priorities, not as already standardised commercial deployments. That distinction is especially important for energy islands, where later interconnector routes could alter initial topology and equipment specification. [VS52-07]

For manufacturers, interoperability can create both opportunity and margin pressure. Common grid-level interfaces may expand the eligible supplier base, but they also demand additional validation, model disclosure, fault-study compatibility and long-term software governance. For transmission owners, modular expansion becomes worthwhile only if new terminals can be added without jeopardising reliability or creating vendor lock-in at the system-control layer.

06 / SUPPLY

Supplier competition is decided in system integration and lifecycle support

VSC stations incorporate expensive, specialised subsystems and are generally sold through engineered project packages. Procurement includes converter transformers, valve halls, cooling plant, AC and DC switchgear, communications and protection and testing services. Scope can be split across a lead converter contractor, marine/cable contractor and civil partner, leaving the owner to manage interactions and commissioning. The number of project press releases involving a supplier is not a meaningful standalone measure of converter market share.

Long-lead components and factory capacity can influence both schedule and tender competition. Operators seeking several stations within a short construction window need credible supply-slot commitments and serviceability across their installed base. Preventive maintenance, spares strategy and software lifecycle support become important economic variables because converter outages can affect an entire high-capacity corridor. Onshore spare access and offshore replacement logistics should not be priced as though they were the same task.

Project qualification therefore requires evidence of comparable grid behaviour, tested electromagnetic and harmonic design, factory and site commissioning resources, cyber-resilient controls and a supported spares portfolio. Companies with repeatable MMC modules may benefit from platform economies, but every station still depends on site-specific transformers, fault levels, connection requirements and civil works.

07 / OUTLOOK

To 2034, proven control performance will matter as much as MW rating

The near-term VSC market has concrete operating and contractual evidence. SunZia establishes a large commissioned project; European owners are moving additional projects through supplier award, manufacture and construction. Commissioning timetables extend into the next decade for some offshore systems, so 2026 orders and 2034 operational outcomes should not be combined into a single installation statistic. [VS52-01] [VS52-08]

The strongest medium-term commercial opportunity is likely to favour suppliers able to deliver multi-gigawatt capacity while meeting challenging AC-system performance requirements and maintaining high availability. The larger step toward coordinated hybrid DC grids depends on protection hardware, interoperable control interfaces and multi-vendor system testing. ENTSO-E’s roadmap confirms why these remain priorities rather than completed standards. [VS52-07]

For buyers, the appropriate comparison is cost and risk over the asset life: equipment and civil expenditure, losses, reliability, support services, operational flexibility and the value of controllable power exchange. For research buyers, the most reliable market signals remain signed project scopes, independently verifiable commissioning dates and measured operational performance. Capability brochures and long-horizon grid plans help explain technology direction, but they do not substitute for executable procurement.

08 / PRIMARY REFERENCES

Primary sources

  1. [VS52-01] Hitachi Energy — SunZia HVDC Light commissioned (2026-06-19)
  2. [VS52-02] Siemens Energy — HVDC PLUS: VSC and modular multilevel converter architecture
  3. [VS52-03] Hitachi Energy — HVDC Light VSC technology and applications
  4. [VS52-04] Hitachi Energy — Applying grid-forming converters to enhance stability (2026-04)
  5. [VS52-05] National Grid — EGL3 signed converter and cable contracts (2026-03-04)
  6. [VS52-06] Siemens Energy — SuedLink DC3 converter stations and HVDC transformers
  7. [VS52-07] ENTSO-E — Research, Development and Innovation Roadmap 2024–2034 (2024-07-10)
  8. [VS52-08] Eiffage — NSC2 2 GW HVDC converter platform award (2026-06-18)
  9. [VS52-09] 50Hertz — Bornholm Energy Island connection
  10. [VS52-10] SSEN Transmission — EGL2 converter station construction, Nov 2026 (2026-11-06)